Project Description

Project Description:

The Southern Gardens Orange Juice facility is a processing plant that frequently runs 24 hours a day during the harvest season. PTI was called in on two occasions during the 2006 and 2007 harvest seasons to deal with leaks in the 10 inch onsite underground process water drainage system. The pipe is 14 feet under ground and the leaks had created voids and structural cave-ins around critical cooling towers and processing equipment. PTI was able to provide a solution with custom lining material and epoxy that would not fail under the wide range of PH criteria and temperature differentials. The plant continued its normal operation during the lining process.

Project Details:

  • Coming Soon

Location:

Broward County, FL